The plan, which calls for a new 35,000-square-foot facility, will involve the demolition of the airport’s existing terminal. The terminal will be constructed alongside the existing terminal, which will remain open until the project is complete. The company plans to provide preconstruction and construction management at risk services for the terminal facility.

The scope of the project includes a general reconfiguration of existing parking lots, the construction of two new parking lots, and a new airport circulation roadway. The new facility will accommodate ticketing operations, baggage claim, airport management offices, airline offices, passenger and baggage screening areas, a restaurant, gift shop, and secure and non-secure holding areas.

The construction of the terminal is scheduled to begin in September 2009 and will be completed by October 2010.

The new terminal, which was designed by AECOM Earth Tech, will be built to achieve LEED Silver certification from the U.S. Green Building Council.